BobaChewie
Member
- Apr 3, 2024
- 18
- 12
Our building permit turn-around time depends on the project classification. Over the Counter (OTC) Plan Checks are done within the same day, usually 30 mins to 1.5 hrs delegated per OTC Plan Check. Expanded Counter Plan Checks (ECPC) are typically 1.5-2 weeks. Regular Plan Checks are about 3-5 weeks, depending on the department load at the time of submittal. Express permits are typically done within 20 minutes, unless there are certain procedures the project requires such as obtaining clearances from other departments.